top of page
Search

October Outlook

rneil37

September of 2022 marked some milestones for the 1951 Shattuck project. The 200 ft Tower Crane was set into place.
















After pouring a protective layer of concrete, installation of below grade waterproofing commenced. The below grade waterproofing is an important aspect of the project as it keeps the water out of the building's basement floors.














Over the next several months you will see a regular cycle of trucks driving on and off site as rebar and concrete are put in place.














The mat foundation will be poured later this month. About 2800 cubic yards of concrete will be poured over the course of 12 hours. There will be three pump trucks set up like the one seen below.



Cal Bear's football season is underway, and we will be coordinating work on days they do not have home games. Go Bears!


_________________________________________________________________________________


The purpose of this blog is to provide the surrounding community with monthly updates regarding construction progress, and what can be expected in the month ahead. If you have questions, feel free to comment below, or email me directly, and I will do my best to address any questions or concerns in the next monthly update.



Cheers!


Katie Chisholm

WEBCOR

Senior Project Manager




60 views0 comments

Recent Posts

See All

Kommentare


  • Facebook
  • Twitter
  • LinkedIn

©2022 by Webcor Builders 1951 Shattuck. Proudly created with Wix.com

bottom of page