top of page
Search
rneil37

Hello October 2023


Exteriors: CCAPP have been completed besides the panels scheduled to be installed after the personnel hoist comes down. You will start to see glass guard rail and some terrace doors installed. The remaining guardrail and terrace doors will be completed later this fall.














Roof: Hot Rubberized Asphalt (HRA) was completed on the roof and we are are now working on completing the Plaster on the Penthouse's.


Interiors: The train is in full force ahead on the interiors. Wall framing will be wrapping up later this month and production drywall has begun. The MEP trade partners are working on final rough in.
















It was announced by Grosvenor that 1951 Shattuck will be named 'Ace'!


_________________________________________________________________________________


The purpose of this blog is to provide the surrounding community with monthly updates regarding construction progress, and what can be expected in the month ahead. If you have questions, feel free to comment below, or email me directly, and I will do my best to address any questions or concerns in the next monthly update.


Cheers!


Katie Chisholm

WEBCOR

Senior Project Manager




75 views0 comments

Recent Posts

See All

Comentarii


bottom of page