Jumping into 2023


During the last part of 2022 Level 1 was officially poured! This is considered a milestone event, since everything prior to this stage has been below grade work. It's all up from here.

















We are preparing for the first elevated deck in early 2023! This formwork work will continue up the building until the last level is poured.


The Concrete placing boom was set in place. This piece of equipment is used for placing concrete rather than having a concrete pump truck on the street, it will be able to reach the whole site as the building goes up in height.















The sequence of installing rebar, formwork, pouring columns and decks will continue up the building over the next several months. You will see a regular cycle of trucks driving on and off site as rebar and concrete are put in place and bringing all this material on site SAFELY!












Meet a team member! Colin is the assistant Project Manager on the 1951 Shattuck Project. He has been with Webcor for 5 years and worked on approximately 4 projects. Feel free to say hi the next time you see him!














_________________________________________________________________________________

The purpose of this blog is to provide the surrounding community with monthly updates regarding construction progress, and what can be expected in the month ahead. If you have questions, feel free to comment below, or email me directly, and I will do my best to address any questions or concerns in the next monthly update.


Cheers!


Katie Chisholm

WEBCOR

Senior Project Manager