top of page
Search
rneil37

April Showers Brings May Towers

Future night noise dates have been posted to the home page and will continue to be updated throughout the project.


We have poured all the way through Level 11. Driving by our building this month you will see Level 12 being poured.


















The priority pass of the interior has just started. We have drywall started on B2 through Level 3 and certain door frames have have been installed.














Elevator separator beams have been installed though Level 7 and will continue up the building. These beams separate the two different elevator cars from one another.


_________________________________________________________________________________

The purpose of this blog is to provide the surrounding community with monthly updates regarding construction progress, and what can be expected in the month ahead. If you have questions, feel free to comment below, or email me directly, and I will do my best to address any questions or concerns in the next monthly update.


Cheers!


Katie Chisholm

WEBCOR

Senior Project Manager

35 views0 comments

Recent Posts

See All

Comentarios


bottom of page